S. No. शीर्षक Theme Total Cost (Rs. Cr) Implementing Agency Project Status Port State Capacity Addition Planned Unit of Capacity Addition
1 2 to 4 laning of NH-169 from Mangalore to Mudabidri Port Connectivity 280 NHAI Under Implementation NMPT Karnataka 35 Km