S. No. Title Theme Total Cost (Rs. Cr) Implementing Agency Project Status Port State Capacity Addition Planned Unit of Capacity Addition
71 RoB cum Flyover at Ranichak level crossing at KoPT Port Connectivity 128 NHAI Under Implementation Kolkata West Bengal 5 Km
72 Rail Obulavaripalle-Venkatachalam (95 km) Port Connectivity 1,825 Indian Railways Under Implementation Krishnapatnam Andhra Pradesh 95 Km
73 Doubling of line Vijaywada-Gudivada- Bhimavaram-Narasapur, Gudivada-Machlipatnam and Bhimavaram-Nidadavolu (221 km) Port Connectivity 1,504 Indian Railways Under Implementation Machilipatnam Andhra Pradesh 221 Km
74 Doubling of Vijayawada- Machilipatnam Railway line Port Connectivity 550 Indian Railways Under Implementation Machilipatnam Andhra Pradesh 80 Km
75 LNG Import Terminal at Mundra Port Modernization 5,040 MoPNG Under Implementation Mundra Gujarat 5.0 MTPA
76 Kotipalli- Narsapur New BG Line (57.21 Km) Port Connectivity 2,120 Indian Railways Under Implementation Kakinada Andhra Pradesh 57.21 Km
77 Bhadrachalam- Kovvuru New BG Line (151 Km) Port Connectivity 1,500 Indian Railways DPR Prepared Kakinada Andhra Pradesh 151 Km
78 Providing a direct connection between OEC and Western Sector jointing at NAD Curve from E.Co. Rly. Port Connectivity 20 IPRCL Under Implementation Vizag Andhra Pradesh 6 Km
79 Connection of dead end line at North of R&D yard to Eastern Grid (Third line) from E.Co.Rlys. Port Connectivity 13 IPRCL Under Implementation Vizag Andhra Pradesh 2.2 Km
80 Extension of line No. 11 to 15 to full length at R&D yard. Port Connectivity 18 IPRCL Under Implementation Vizag Andhra Pradesh 5 Km