S. No. Title Theme Total Cost (Rs. Cr) Implementing Agency Project Status Port State Capacity Addition Planned Unit of Capacity Addition
61 New Port - Bhavanapadu Port Modernization 4000 Department of Ports, GoAP DPR Prepared Bhavanupadu Andhra Pradesh 40 MTPA
62 New Port at Machhilipatnam (Phase 1) Port Modernization 11924 Department of Ports, GoAP DPR Prepared Machilipatnam Andhra Pradesh 50 MTPA
63 Construction of a passenger Jetty at Kalingapatnam Port Modernization 48 APTDC DPR Under Preparation Others Andhra Pradesh NA
64 Construction of a passenger Jetty at Bheemunipatnam Port Modernization 79 APTDC DPR Under Preparation Others Andhra Pradesh NA
65 Construction of Tourism Passenger Jetty at Maypadu, SPS Nellore Port Modernization 58 APTDC DPR Under Preparation Others Andhra Pradesh NA
66 Construction of Tourism Passenger Jetty at Manginapudi, Krishna Port Modernization 74 APTDC DPR Under Preparation Others Andhra Pradesh NA
67 Construction of Passenger Jetty at Baruva in Srikakulam Port Modernization 59 APTDC DPR Under Preparation Others Andhra Pradesh NA
68 Development of Passenger Jetty, Sea Plane Jetty and upgradation of existing jetty at Kakinada Port Modernization 58 APTDC DPR Prepared Kakinada Andhra Pradesh NA
69 Construction of passenger jetty at Bhavani island, Krishna district Port Modernization 22 APTDC Under Implementation Others Andhra Pradesh NA
70 Upgrading and modernisation of Cruise Terminal at BPX (Indira Dock) - Mumbai Port Modernization 197 MbPT Under Implementation Mumbai Maharashtra NA