571 Development of Dry Dock at Timber Pond/Boat basin at Chennai port or Development of Marina Port Modernization 315 ChPT DPR to be Prepared Chennai Tamil Nadu NA MTPA
572 Construction of Bunker berth at Chennai Port Port Modernization 44 ChPT Under Implementation Chennai Tamil Nadu 1.0 MTPA
573 Development of paved storage yard at Chennai Port for handling export cargo Port Modernization 54 ChPT Under Implementation Chennai Tamil Nadu NA MTPA
574 Coastal Cargo Berth at ChPT Port Modernization 80 ChPT Under Implementation Chennai Tamil Nadu 1.0 MTPA
575 Strengthening of existing revetment at eastern seashore of Chennai Port Port Modernization 63 ChPT Completed Chennai Tamil Nadu NA
576 Development of Cruise Passenger Facilitation Centre at Chennai Port Trust Port Modernization 18 ChPT Completed Chennai Tamil Nadu NA MTPA